Practice Management Member Conversations

 View Only
  • 1.  Use of A103 Contract

    Posted 03-13-2012 11:43 AM
    This message has been cross posted to the following Discussion Forums: Small Project Practitioners and Practice Management Member Conversations .
    -------------------------------------------


    -------------------------------------------
    Benjamin Albury Intl. Assoc. AIA
    Senior Partner
    Albury Associates Limited
    Nassau
    When using the A103 Form of Contract(Cost of Works Plus Fee without a Guaranteed Maximum Price) there is obviously no Original Contract Sum(Line 1), when completing the G702 Document, Application and Certificate for Payment.
    We have noted NA (Not Applicabe) in the dollar value column leading to the Total Completed & Stored line (Line4).
    Is there another recommendation for completing this portion of the Certificate For Payment?
    A response would be greatly appreciated.
    Benjamin.
    -------------------------------------------
    AIA Business Academy: A high-impact, four-part intensive program starting June 9. Earn 22.75 LUs. Click here to learn more.