Here is a non-spec section list. It can be used in a letter to the GC/CM or put in spec.
Closeout Check list
1. Certificate of Occupancy
a. Temporary C of O - Date
b. Permanent C of O - Date
2. Substantial Completion Certificate
a. Interior design team punch list
i. Final date of complete punch list
b. Punch List completion verification (value of incomplete items to be included on SC)
i. Final date of completed punch list
ii. __ days to complete Punch List/Completion list
c. List of incomplete / added scope
i. Date of completion
ii. Value of scope
d. Transfer of Utilities
i. Water - Date
ii. Gas - Date
iii. Electrical - Date
3. Final Completion Procedures
a. CO review / final cost review
b. Final Application of Payment
c. Certificate of Insurance
i. Bond release forms -
d. Warranties & Closeout submittals (Need to determine date of completion ???)
i. Warranty submittals/letters per required divisions
1. Pest control, HVAC, roofing, etc….
ii. As-Builts
iii. O&M's
iv. Owner training (Pond, HVAC, lighting controls, AV, etc..)
v. Attic stock (Transmittals)
vi. TAB reports
vii. USB closeout package from GC
e. AIA Close-Out Documents
i. G706 - Contractor's Affidavit of Payment of Debts & Claims
ii. G706A – Contractor's Affidavit of Release of Liens
iii. G707 – Consent of Surety to Final Payment
4. Final Completion form or letter (signed by all parties if nec.)
------------------------------
David Heuring, AIA, CCCA, NCARB. Architect, Partner
RDG Schutte Wilscam Birge, Inc.
Omaha, NE - Ft. Myers Beach, FL
------------------------------
Original Message:
Sent: 08-23-2024 01:57 AM
From: Navaz Fouladzari AIA
Subject: Close out documents Checklist
Hi everyone
Does anyone have a checklist for the documents needed for closeout?
Please share any sources regarding this.
Thank you so much for your attention and participation.
Navaz Fouladzari
MArch, Architect OAA, AIBC, AIA, MRAIC, MRIBA