Mr. Shapiro.
What a one side, single minded view of the situation.
Did you factor in that.
1. not all submittals by the contractor are reviewed solely by the architect. Other consultants are involved, and it takes time to distribute and coordinate all of these reviews, especially to other offices in other communities.
2. not all submittals are compliant with the contract documents (as per Mr Beyer comment).
3. Not all submittals are submittals, sometimes they are in fact "material substitution" not identified as such.
4. as we are talking about time, often the submittals are not distributed to the architect in an appropriately fast manner.
5. sometimes the submittals are not reviewed by the contractor prior to being sent onto the architect.
6. (this list may not be complete)
Mr. Shapiro is making an issue of something in a very divisive manner, failing to identify that at times the issue a contractor has with the submittal process is as a result of their own actions. Actions such as
1. issues they have with coordinating the awarding of sub contractors, coordinating materials order, etc.
2. issuing submittals by the slower cheapest route possible and expecting it then to be reviewed and returned in the quickest possible manner. (Question, is shipping time factor in/reduce the time allotted for review.)
3. attempting to end around the contract documents by submitting a material substitution as a shop drawing.
Are there going to be issues on the architects side. Yes there will be. Whether it be an issue with how a specific practice performs as whole or of a specific employee / consultant.
But to pretend in your post that the contractor is without a factor in this is not addressing the entire story. Which only adds to creating a further division within the industry. Which I find unacceptable.
M. Chamoff I think brings up a good point. That being when a contractor can be involved early, it does provide an opportunity to bring in their input and create for a better overall project. Often our designs have to be based upon assumptions or generalizations about the means and methods employed by the contractor, but still be responsive to an compliant with codes/ordinances, planning approvals, and owners requirements. However, not all contractors (for fairness architects) are interested in taking advantage of this opportunity. A situation which is very disappointing when it occurs, for the Owner has failed to receive the benefit of a more complete collaboration on their project.
-------------------------------------------
Chad Berreau Assoc. AIA
Cottage Grove MN
-------------------------------------------
Original Message:
Sent: 04-28-2011 14:24
From: Steven Shapiro
Subject: The Architect-Contractor Smackdown: Using specifications and drawing notes to create an end-run around the contract
This message has been cross posted to the following Discussion Forums: Project Delivery and Construction Contract Administration .
-------------------------------------------
The Architect-Contractor Smackdown
Using specifications and drawing notes to create an end-run around the contract
by Steven G. Shapiro *This entry was originally posted to AIA Archiblog in June 2008.
During a typical design and construction project, the general contractor and architect work closely for the duration of a project, often without a direct contract, to legally define the scope of their relationship. In the absence of a contract, the parties often jockey to create greater rights to protect their own interest. Lately, it seems that the architecture community has expanded its rights to the detriment of the contractors.
Consider, for example, an architecture firm designing an office building and a general contractor engaged in its construction. By the terms of its agreement with the owner, the general contractor delivers a submittal to the architect for review and may contractually expect a response in 7 business days. By the terms of the drawing notes and specifications, however, the architect may have reserved 10 business days to respond to the submittal.
This simple example illustrates the seemingly endless tension in the allocation of the rights and duties between the general contractor and the architect. In the traditional delivery method of design-bid-build (or various hybrid forms of project delivery), the architect holds a contract with the owner regarding the duties of design and contract administration. As part of its engagement, the architect then issues drawings and specifications setting forth the design of the project.
At the same time, the general contractor negotiates a separate contract with the owner regarding construction services. In the construction services agreement, the drawings and specifications are incorporated into the document to form the contract documents. These contract documents bind the GC to their dictates and directions and, at times, conflict with the terms and conditions of the construction agreement.
By appearances, the architectural community has recently expanded the reach of the specifications and drawing notes to place undue risk to the contractor. As a construction manager and allied member of the AIA, I appreciate the agenda of the architects. The zeal to re-allocate risk to the contractor is now beyond the norm.
Legal disputes, or perhaps battles of negotiation, are likely brewing between the GC community and developers, and, by extension, architects. In the near-future, I would expect to see contractors seeking to limit the power of the architects to set forth their working relationship. In the absence of resolution, I can envision litigation to resolve these issues.
*Steven G. Shapiro, an allied member of the AIA and former commercial real estate development attorney, is an adjunct professor at the University of Maryland and a project manager at a large general contractor. He can be reached at stevengshapiro@aol.com.
This entry represents the informed opinion of the author only. It is intended for general information purposes only and does not constitute legal advice. The reader should consult with legal counsel to determine the complex interaction of laws, suggestions, and illustrations with specific situations.
-------------------------------------------
Steven Shapiro
Project Manager
The Whiting-Turner Contracting Company
Bethesda MD
-------------------------------------------