I can say they are NOT Records Documents or As Builts, or part of the typical AIA Contract (Unless you kept in
AIA B101-2017 "§ 4.1.1.14 Conformed documents for construction" but we do occasionally offer it when the Contractor is less savvy and doesn't do Revit or build a model themselves. We have used the following language to help define the additional service to provide Conformed Drawings:
• Conformed Drawings include the bid drawings, updated to include all changes made by addendum during the bid process and all awarded alternates.
• Addendum drawings shall be incorporated into the drawing sheets for the set.
• Addendum drawings shall not be on separate layouts or sheets unless an entire new sheet has been issued and added to the complete set of drawings.
• Conformed drawing hard-copies and PDF files intended for use during construction shall be signed and stamped by the responsible professional.
• Electronic submittals of conformed CAD/BIM files shall not include electronic signatures or professional stamps.
• Each sheet of conformed electronic files must contain the following block:
• Locate the block in the lower right corner of the drawing area to the left of the title block. If sheet contents conflict with the stamp, adjust the location of the stamp.
------------------------------