Construction Contract Administration

 View Only
Expand all | Collapse all

Order of Precedence for Contract Documents

  • 1.  Order of Precedence for Contract Documents

    Posted 03-11-2025 12:36 PM

    Is there a preferred order of precedence for Contract Docs? and if so which section in Div01 should it be listed.  My understanding is that AIA contracts has tried to flatten the requirement and give equal weight to drawings vs specifications. This (AIA direction) I find to be confusing as typically this is where the most conflicts happen. Thoughts?



    ------------------------------
    Janene Christopher AIA
    Steinberg Hart
    San Diego CA
    ------------------------------
    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 2.  RE: Order of Precedence for Contract Documents

    Posted 03-11-2025 07:29 PM

    An order of precedence (or preference) implies that certain documents are inherently more likely to be correct.

    I would suggest that written contract modifications (change orders) are #1, then the owner-contractor agreement. 

    After that - are specifications inherently more correct than drawings? If those specs were simply reused from another job, maybe not.

    [ I suspect,  without proof, that "specs > drawings comes from lawyers being better at presenting words to juries, than explaining a drawing. ]

    Details > smaller scale drawings ? Again, when details are just selected from a catalog and not edited, how trustworthy should they be?

    One consultant's drawings over another's?  what if architect and structural engineer have dimensional differences for a grid line? And thus there isn't space for a duct of size shown on mechanical drawings?  Or if a sprinkler subcontractor designs pipes where ducts should be, hangs the pipes, and there is mutual finger pointing? (General contractors often pass contractual coordination requirements down in subcontracts (and then don't exercise their own responsibility).

    "Documents are complementary, ask questions if you think there is a conflict" can cause "extra work" for architects who don't coordinate in the first place.



    ------------------------------
    Joel Niemi AIA
    Joel Niemi Architect
    Snohomish, WA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 3.  RE: Order of Precedence for Contract Documents

    Posted 03-13-2025 07:49 AM

    Drawings and specifications are complementary of equal significance or weight.  What is shown on one document is implied on all.  The contractor is obligated by contract to review each document and notify the architect of discrepancies.

     

    Blessings,

     

    Walter W. Wilson, AIA Architect

    Email – walter@wwwilsonarchitects.com

    214.725.9348

     

    Web: https://wwwilsonarchitects.com

     

    This email may contain privileged communications. If you are not one of the intended recipients, please immediately delete or destroy all copies or versions you have of this message and notify the sender at (214) 725-9348 or walter@wwwilsonarchitects.com in order that we may take steps to prevent any further disclosures.

     

     




    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 4.  RE: Order of Precedence for Contract Documents

    Posted 03-13-2025 08:02 AM

    Drawings and specifications are complementary of equal significance or weight.  What is shown on one is implied on all.  The contractor is obligated by contract to review each document and notify the architect of discrepancies.



    ------------------------------
    www
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 5.  RE: Order of Precedence for Contract Documents

    Posted 03-13-2025 05:39 PM

    Joel, what you describe is the process the courts/ADR would likely use when interpreting the documents in response to a claim. 



    ------------------------------
    Ronald Geren, AIA, FCSI, Distinguished Member, CCS, CCCA, CDT, SCIP
    RLGA Technical Services LLC
    Scottsdale AZ
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 6.  RE: Order of Precedence for Contract Documents

    Posted 03-12-2025 05:28 PM

    If you are using AIA Contract Documents, there is no precedence in the contract documents. AIA Document A201, Section 1.2.1, states, "The Contract Documents are complementary, and what is required by one shall be as binding as if required by all." If any document has precedence over another document, that would be the Owner-Contractor agreement. If there is a conflict in the Contract Documents, A201, Section 3.2.2, requires the contractor to review the Contract Documents and report promptly to the Architect "any errors, inconsistencies or omissions discovered."

    Relying on an order of precedence could produce unexpected or unintended consequences. 



    ------------------------------
    Ronald Geren, AIA, FCSI, Distinguished Member, CCS, CCCA, CDT, SCIP
    RLGA Technical Services LLC
    Scottsdale AZ
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 7.  RE: Order of Precedence for Contract Documents

    Posted 03-13-2025 05:45 PM

    The response from Ron Geren, AIA is spot on. In my career, I have found that attorneys and contractors prefer to define an order of precedence as it provides simplicity for their purposes in interpreting the documents as opposed to the Architect being the interpreter and making reasonable judgements. Establishing an order of precedence for certain aspects of the Contract Documents may be desirable, particularly with respect to information issued subsequent to previously issued information. For example, addenda having precedent over previously issued documentation, although establishing precedent for such chronologically issued information is generally superfluous as the precedence is clear.

    In no instance, however, should precedence be given to specifications over drawings, or vice versa. Specifications establish the level of quality and set forth other information such as the acceptable products and the processes to be followed. Drawings illustrate the extent and relationship of the physical elements of the project. These are quite different purposes which is why the specifications and drawings must be crafted to complement one another. It is difficult, if not impossible, to correlate such information if either the specifications or the drawings take precedent over the other.

    In no case should submittals, including shop drawings, ever be included in an order of precedence as these are NOT Contract Documents and, therefore, they should never be considered to have any precedence.



    ------------------------------
    Mark I. Baum, AIA
    Mark I. Baum Architect LLC
    New Orleans, LA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 8.  RE: Order of Precedence for Contract Documents

    Posted 03-14-2025 05:33 PM
    In its simplest terms, the Drawings and Specifications are “Contract Documents” and provide the basis for the contract between the Owner and General Contractor. The Specifications should define “What” it is and the Drawings should define “Where” it is. Neither has precedence or priority over the other, nor should one exist without the other.

    The Submittals, including Product Data, Shop Drawings, Coordination Drawings, etc are “Construction Documents” to be used in the execution of that Contract.

    Robert Brumfield, AIA, NCARB


    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 9.  RE: Order of Precedence for Contract Documents

    Posted 03-13-2025 08:49 AM

    Typically, we rely on and enforce the verbiage in the A201 that Ronald mentioned (similar language is also in the A232) with varied success. We have had clients that in their procurement or general conditions documents in Div 00 or 01, indicate an order of precedence for the documents (specs>drawings>general conditions). We have also had both the A201 or A232 language as well as the owner's language on the same project, so that makes for an even more confusing discussion.

    Certainly, it isn't a "fun discussion" to have when there is a conflict in the documents. You have the balance of enforcing the documents while trying to save face/keep your integrity. The contractor "bought" the Contract Documents, so it is up to them to read them and bring up conflicts and questions at bid time. That being said, architects need to continually do what we can to improve documents through QA/QC.



    ------------------------------
    Sharon Day AIA
    GWWO Architects
    Baltimore MD
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 10.  RE: Order of Precedence for Contract Documents

    Posted 03-13-2025 06:23 PM
    Janene,
    So far it seems like the comments have:
    1) Confirmed that the AIA General Conditions are "flat".
    2) Stated that's what is intended.
    3) Had a few "order of precedence assumes some documents are inherently more correct than others" statements.

    [regarding #3, I will assure you that at some point it will come to bite you, and the flexibility of being able to interpret differing requirements in the best interest of the project is useful for all concerned.]

    But, to address the "where to state an order of precedence", I suggest putting it in either edited General Conditions (assumes all concerned read them and comprehend edits) or in Supplementary/Special Conditions, which is the place to call particular attention to unique factors. 
    Whichever route you take, talk about it in the pre-bid and pre-construction meetings.  




    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 11.  RE: Order of Precedence for Contract Documents

    Posted 03-18-2025 01:00 PM

    If there is an order of precedence, this is a contractual requirement, not an administrative (Division 01) requirement.  I've worked in the past on a lot of public projects that do have an order of precedence, and generally it goes like this:  Addenda; General and Supplementary Conditions; specifications; drawings, starting with details and going to the larger sheets.  Note that at the beginning, it goes in order of "what was issued last"; then the contractual requirements, the specifications -- not because they are inherently better but because words tend to be more easily interpreted by a non-architect arbiter; and then in the drawings, the details supercede the full size drawings because the assumption is that the details are custom fabricated for the project and more explicit.   

    Note that Division 01 is administrative -- it explicates the requirements of the contract, it does not create new requirements.  

    I have had  projects  in the past where we declared an order of precedence only for the bidding period.  When I did a lot of publicly bid projects, we found that contractors were reluctant to ask questions about document conflicts because they didn't want to tip their hand to the other bidders.  In those cases, all bidding questions had to be submitted in writing and then the question and the response was published in an addendum issued before bidding.  What that ended up with was ridiculous  situations where we specified one thing and the ceiling plans showed another thing, so the contractors would completely leave that out of their bid due to a "conflict".  For the convenience of those projects we would state an order of precedence for the bid period only, so that the contractors had some guidelines for their bidding process.  After that, the contractual requirements "complementary and ask the questions" would then apply. 



    ------------------------------
    Anne Whitacre FCSI
    Senior Specification Writer, Principal
    HOK
    San Francisco CA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 12.  RE: Order of Precedence for Contract Documents

    Posted 03-20-2025 02:52 PM
    Edited by James Woody, AIA 03-20-2025 02:52 PM

    This is excellent topic. I have seen the following included in the Supplementary General Conditions on a handful of projects.

    1.1 BASIC DEFINITIONS

    1.1.1 Add the following to subparagraph 1.1.1:Conflicts or discrepancies among the Contract Documents shall be resolved the following order of priority:

    1. The Agreement and Amendments to the Agreement and revisions of the Agreement by Addenda with those of later date taking precedence over those of earlier date;
    2. The Supplementary General Conditions;
    3. The General Conditions;
    4. Drawings and Specifications; Drawings govern Specifications for quantity and location; and Specifications govern Drawings for quality and performance. In the event of ambiguity in quantity or quality, the greater quantity and better quality shall govern; and
    5. Figured dimensions govern scale dimensions, and large-scale Drawings govern small scale Drawings.

    When conflicts have risen on past projects, I have pointed to this as a precedence.

    Hope this helps,

     



    ------------------------------
    James Woody AIA
    Perkins + Will
    Palmyra VA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 13.  RE: Order of Precedence for Contract Documents

    Posted 07-30-2025 10:51 AM

    James do you use this language in the supplementary conditions for every project as a standard? Or is it for special situations like Anne was alluding to for bigger publicly bid projects? And if thats the case how do you decide where to include it? Just curious. 

    Anne it sounds like for you this is a specialized use case. How do you decide when to use this strategy and language? (Also, as an aside, bidders really just left out building components shown on the drawings and specs because of conflicts?? Couldn't you just include something in the instructions to bidders about that being disqualifying and instruct everyone to ask the question and or include assumptions if it was after the question period / addenda were issued? That sounds wild to me but I have certainly seen a lot of craziness when it comes to bidding)



    ------------------------------
    Jessica Saravia AIA
    DMAC Architecture
    Evanston IL
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 14.  RE: Order of Precedence for Contract Documents

    Posted 07-31-2025 02:55 PM

    The order of precedence text listed by James Woody comes from AIA A503-2018 Guide to Supplementary Conditions - a useful and underutilized document. I don't like to include an order of precedence in the documents, as it could lead to the Contractor determining for themselves how to resolve a conflict in the documents rather than submitting it to the Architect for interpretation This is, I believe, why the AIA Contract Documents Committee has long resisted the pressure to include an order of precedence in the AIA A201. The ultimate goal of the AIA documents is to resolve conflicts and deliver the project that meets the Owner's requirements. Sometimes that means the Architect has to determine that resolution, exposing their firm to claims due to conflicts in their own documents. Another reason to respect the AIA documents.



    ------------------------------
    Philip Kabza AIA
    SpecGuy Specifications Consultants
    Mount Dora FL
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 15.  RE: Order of Precedence for Contract Documents

    Posted 07-31-2025 03:48 PM

    Thanks Phillip. 

    I have used the order of precedence to support my position during change order negotiations. I found it particularly useful on GMPs, when the contractor wants to argue what their subcontractor bought vs what they owe.

    As arbiter of the contract for construction there will be cases when we have to determine if a change was the result of an error or omission. And there will be errors and omissions. 

    What this conversation highlights is the AIA Contract Documents are designed to work together. They work as a suite of documents vs standalone. When an owner elects to use an AIA contract with the architect and an AIA contract with the contractor, that is the best-case scenario as the contracts talk to and reference one another. It also ensures that both contracts are based on a set of definitions, which is also an AIA document, so there is no (or less) ubiquity. 

    I may use this topic in one of our future Architects in Work Boots workshops at the AIA Convention. Good stuff.

    Jim Woody, AIA



    ------------------------------
    James Woody AIA
    Perkins + Will
    Palmyra VA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 16.  RE: Order of Precedence for Contract Documents

    Posted 07-31-2025 04:21 PM

    Jim,

     

    Hurray! I ran into this thread after having spent a couple of days moving a project from a disgusting set of CM Division 00 documents to the AIA documents with the support of the Architect.

     

    I have maintained MasterSpec's Division 01 for about 12 years, created their Division 00, and also updated 00 last year. I'm kind of a fish in water on front end issues.

     

    It's good to know there are good applications for the order of precedence clauses. I've kept them in our master 073000 greyed out so that they are still there for conversation depending on the delivery method. As a consulting specifier, we're not in the trenches the way our architect clients are.

     

    Best regards,

     

    Phil

     

    Phil Kabza, FCSI CCS AIA

    SpecGuy Specifications Consultants

    Building relationships through Education

    www.SpecGuy.com

    Phil@SpecGuy.com

    w704.367.1991 m704.618.1750

     




    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 17.  RE: Order of Precedence for Contract Documents

    Posted 07-31-2025 10:39 PM

    AIA Documents are drafted from three perspectives.  First, they are to represent current practice, not to create new practice. Next, the documents are drafted so that all related documents are completely coordinated.  Last, they are written to represent best practices, tested through wide experience and legal cases. The documents need to work for small firms to large firms, for experienced practitioners to inexperienced practitioners, and even work when the incorrect/not best document is selected. 

    So, the basic AIA approach to Contract Documents is that all contract documents are considered equal and mutually inter-supportive of each other. AIA A503-2018 Guide to Supplementary Conditions contains suggested or optional language for situations that either are not the best of best practice or not the most common practice but still occur often enough for AIA to offer suggested best practices language that sill works and is coordinated with their other documents.

    Whether you use an order of precedence supplemental language is a decision for how you practice.  On one hand, if a conflict comes up between contract documents and all are considered equal, the architect ethically must select the correct option or interpretation.  That said, as often as not, the contractor is going to accuse the architect of making the decision that is best for the architect, sort of having it both ways. That's a tough situation.

    With precedence of documents, it's both good- we know what will be the determiner- and the bad- that if the higher priority document is wrong and the lower priority document is right- you're stuck.

    In my past practices, we did have a precedence of documents condition for the following reason.  Specifications more often than not were written, including an office master spec, by more experienced staff, while details and drawings often were created by less experienced staff. Given a conflict, we wanted something created by the more experienced staff to take precedence over something created by less experienced staff. Case in point: often specs are written to install something "in strict accordance with the manufacturer's written recommendations." What was on the drawings wasn't perfectly in line with what the manufacturer required.  We had an out- the higher priority document required following the manufacturer's requirements. Whether we succeeded in the argument, at least we had some advantage to start with.



    ------------------------------
    Arlen Solochek, FAIA
    Owner/Principal/Founder
    Arlen Solochek FAIA, Consulting Architect
    Phoenix, AZ
    ArlenSolochek@gmail.com
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 18.  RE: Order of Precedence for Contract Documents

    Posted 08-01-2025 08:27 AM

    Excellent points, Arlen, and thank you for your meaningful contributions to this Knowledge Community! 

    I'm a chapter and verses guy and prefer to have something to point to justify my position vs responding, "because I said so". As you stated, it's a matter of choice and preference.  

    When something is clearly defined in the contract documents, it makes our job easy when it comes to disputes. It's the grey areas where we often find ourselves in trouble. 

    Jim



    ------------------------------
    James Woody AIA
    Perkins + Will
    Palmyra VA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 19.  RE: Order of Precedence for Contract Documents

    Posted 07-31-2025 06:07 PM

    In my consulting role on projects gone bad, I am seeing more precedence clauses in the General Conditions and Owner-Contractor Agreement, especially when the General Contractor is providing preconstruction services and has heavily edited one or both of these two documents.The "assumptions and clarifications" attached to the O-C Agreement is always #1 on the precedence list, typically followed by the Contractor edited General Conditions, with the Architect's Instruments of Service are always last. Precedence Clauses are neither good or bad, but how they are used are! When correctly used by the Architect applying skilled judgement to the unique project circumstances, precedence clauses can assist in clarifying and administering Contract Documents in accordance with the Architect's design intent. However, they can also be used to take advantage of Owners who lack technical and construction contract experience. 



    ------------------------------
    Dennis Hall FAIA
    HALL AEC PA
    Asheville NC
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 20.  RE: Order of Precedence for Contract Documents

    Posted 08-05-2025 02:35 PM
    Dennis brings up an incredibly important point for GMP -  the "Assumptions and Clarifications" also known as the A&C's.  The CM attaches this to the GMP submittal.  This may be deserving of a separate Knowledge Community discussion thread.

    If the A/E team leadership does require the contractor to not track and address these at pricing checks through design there will be potentially big surprises in the GMP package.

    There needs to be time for the A/E team to properly review and comment on any CM@R A&C's at draft stage to call out those to the client that can result in lesser quality, and/or result in A/E team Additional Service Requests to revise the drawings and specs.  

    Beware - If the Owner accepts the submitted GMP with the CM@R's A&C's, the final reviewed and negotiated A&C's should be explicitly attached to and incorporated in the GMP Amendment to the CMAR contract.  It is my understanding that without specific incorporation, the General Conditions and the A/E's drawings/specifications take precedence in interpreting scope and requirements.

    Do others of you have experiences and input to this?

    ---------------------------------------------------------------------

    Michael L. Katzin, AIA
    Member | City of Johns Creek Planning Commission

    ---------------------------------------------------------------------




    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 21.  RE: Order of Precedence for Contract Documents

    Posted 08-05-2025 02:55 PM

    In response to Michael Katzin and in full agreement with his comments, in the limited situations where I have been involved with GMP contracts, the A&C's always tend to be a point of friction later in the project as the Contractor or CM rarely define the items in the same detailed manner as does the Architect in its Instruments of Service. They tend to be vague and are subject to the interpretation of the Contractor, rather than interpretation by the A/E which the AIA A201 requires. Therefore, establishing the A&C's globally as being ahead of the drawings and specifications in precedence can be a slippery slope for the Owner and for the A/E.



    ------------------------------
    Mark I. Baum, AIA
    Mark I. Baum Architect LLC
    New Orleans, LA
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 22.  RE: Order of Precedence for Contract Documents

    Posted 08-05-2025 03:37 PM

    Michael,

    I just read an Owner-Contractor Agreement (A102) where the precedence clause listed the Architect's "plans" as number six in precedence priority and the "specifications" as number 7. Yes, the "Contractor's Proposal" was number 1, which was attached to the O- C Agreement, number 4.  Unfortunately, this is more common than one would like to think.



    ------------------------------
    Dennis Hall FAIA
    HALL AEC PA
    Asheville NC
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 23.  RE: Order of Precedence for Contract Documents

    Posted 08-05-2025 03:47 PM
    A&C's for a CM at Risk/GMP project are standard fare- I don't think that I've ever seen a GMP proposal come through without any qualifications and honestly, they do represent how the CM sees the project and its costs.

    One suggestion for the A&C's issue for order of precedence, since any revisions to the General Conditions should be a negotiation, could be to allow the A&C's to be first listed precedent BUT modify that  request to be:

    1.  If the A&C's impact the Architect's Instruments of Service (as defined, includes your drawings, specifications, models, et.) or professional responsibilities, only the A&C's that both the Architect and Owner review and approve become part of the construction agreement. 
    2. If the A&C's impact only the Owner, only the A&C's that the Owner reviews and approves become part of the construction agreement. (If you want to offer the Owner some assistance in this review, you can add that the Architect must review these but need not approve them.)

    Contractor's shouldn't object to this since an agreement is a "meeting of the minds" and to eliminate future disputes, everyone's mind should meet before accepting A&C's and signing the final agreement. 

    Many of the A&C's are developed at last minute as the Contractor is trying to cover everything and finds there are gaps or unknowns, so advance review and approval often isn't possible. For everyone's protection and in fairness, it has to be emphasized that simply because an A&C is offered and finds its way into the Owner- Contractor agreement shouldn't mean that it's accepted without question. 



    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 24.  RE: Order of Precedence for Contract Documents

    Posted 08-05-2025 04:10 PM

    I think the flaw in your argument is the assumption

     

    " It is my understanding that without specific incorporation, the General Conditions and the A/E's drawings/specifications take precedence in interpreting scope and requirements.".

     

    I simply don't think you can assume this.  And, as one previous employer pointed out to me, the contractor and owner can play golf one Sunday and rewrite their whole basis of assumptions for the contracts.  We deal with this regularly – where a contractor has told us they are "including fees for testing" and then a year later we get a change order for – testing.  Our assumptions have to be explicit and in writing and distributed. 

     

    Anne Whitacre

     

    ANNE WHITACRE  FCSI, CCS, Associate AIA, LEED AP BD+C
    Principal  |  Sr. Specification Writer

    HOK
    One Bush Street, Suite 200  |  San Francisco, CA 94104 USA
    t +1 415 356 8685  m +1 510 388 4333  anne.whitacre@hok.com

    hok.com  privacy policy




    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 25.  RE: Order of Precedence for Contract Documents

    Posted 08-05-2025 05:48 PM

    I've been following the conversation here. I'm still trying to ascertain why we even have the precedence clause. I was "brought up" in this profession to believe there was no precedence) or preference as the case could be) in our documents as we are the "arbiter" so to speak of our documents and therefore if there is conflict we interpret what that resolution should be. I think the "A and C's" fall into a category of their own and if they address an assumption or clarification of our documents then it is incumbent upon us to determine if those "A and C's" are indeed correct. Or, am I missing something here? 



    ------------------------------
    David R Proffitt, AIA
    Nashville TN
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 26.  RE: Order of Precedence for Contract Documents

    Posted 08-06-2025 11:36 AM
    Good point by Anne.

    For our CM at Risk projects, we required the following exhibits from the contractor also to be submitted with its GMP proposal in addition to those required by the AIA Agreement:

    Exhibit XX: A detailed list of assumptions and clarifications made in preparing the Guaranteed Maximum Price Proposal. All assumed or requested changes to the Contract Documents listed by the Construction Manager shall be reviewed with and receive specific written approval of both the Owner and Architect in order to be included in the final accepted GMP Proposal. 

    Exhibit XY: A list of the specific exclusions from the Work, costs, or other items that are contained within the Guaranteed Maximum Price. All Work necessary to complete the Project not listed with the specific exclusions is considered to be included within the Guaranteed Maximum Price. No Work contained in the Contract Documents and Addenda shall be accepted as an Exclusion without a specific separate written notification to the Owner and a specific written agreement by the Owner in advance of submitting the GMP.
     
    These didn't prevent every problem but helped to close a lot of gaps and assumed exclusions.

    For the architect, if you are using AIA's owner-architect agreements, your services and fee are tied to the General Conditions of Construction, which should be included in your O-A agreement.  The architect's agreement states that 

    § 3.6.1.1 The Architect shall provide administration of the Contract between the Owner and the Contractor as set forth below and in AIA Document A201™–2017, General Conditions of the Contract for Construction. If the Owner and Contractor modify AIA Document A201–2017, those modifications shall not affect the Architect's services under this Agreement unless the Owner and the Architect amend this Agreement. (B101-2017)

    So, if the owner and contractor go golfing and completely rewrite the General Conditions, at least the architect's services and fees are protected unless the owner also modifies the architect's agreement.  




    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online


  • 27.  RE: Order of Precedence for Contract Documents

    Posted 08-06-2025 02:34 PM

    I have started a thread under Project Delivery Knowledge Community regarding GMP's and the CM's Assumptions & Clarifications (A&C's). If the A&C's in a GMP become an issue during construction administration, well that is too late to properly deal with A&R's4 properly.   Check out that Project Delivery thread and provide your comments.  https://communityhub.aia.org/discussion/how-to-address-cms-assumptions-clarification-in-a-gmp-submittal#bm00382290-f3bb-443e-b84d-c9a201e3ba6b

    The Construction Administration Knowledge Community comments about A&C's in a CMA@R's GMP submittal seem to come from many perspectives as they relate to the simple idea and philosophy and contract management of the order or precedence of contract documents.  The curiosity I had in thinking about the A&C's in the GMP submittal and order of precedence is simply how do A/E teams manage the review process of of CMA@R GMP and the A&R's section, and how the A/E team negotiate and finalize A&R's that are attached to the CM@R GMP submittal.

    So, I am about how firms manage A&R's -

    1) what do you do during the design and cost phases - do you have the CM@R include a preliminary draft/tracking table of potential A&C's at each pricing or more frequent?

    2) what are any of your firms doing in your continuing education programs to educate and offer CEU sessions to the rising staff on the importance and process to manage the A&R's on GMP projects?

    3) do any of you know if the AIA National has any literature on this topic,

    4) do any of the NCARB ARE 5.0 testing divisions even mention A&C's?  If it doesn't - should it?  I did not find any reference to this in my search of the NCARB ARE 5.0 materials.

    5) did you know the AGC, in partnership with the National Association of State Facilities Administrators (NASFA), has published CM/GC guidelines that address GMP development and Assumptions & Clarifications -- should the AIA address this topic for membership?

    Again - just curious about this topic.



    ------------------------------
    Michael Katzin, AIA
    Johns Creek, GA
    Member - Johns Creek Planning Commission
    ------------------------------

    Safety Assessment Program (SAP) - Become a building evaluator to assist after local disasters - Dec 10-11 online